I'm using your software since 3 weeks but i don't understand the difference between each date when i create a project or an activity.
What is the difference betwen :
Valided
Planned
Real
Requested.

Thank you very much and have a good day 🙂


 
Posté : 11 Juin PM 21:066
(@babynus)
Posts: 14952
Membre Admin
 

Requested = the first request from your customer (his Christmas wish list)
Validated = what you finaly committed with your customer. It is your baseline.
Planned = calculated by PrjeQtOr taking into account work assigned to resources, resources availability and all the constraints on tasks and resoures.
Real = defined from real work allocation (real start date = first date for real work)


 
Posté : 11 Juin PM 22:066
(@jonathan02500)
Posts: 21
Active Member
Début du sujet
 

Thank you very i understand now 🙂
Have a good day. 🙂


 
Posté : 12 Juin PM 12:066