Hi,
In first time, sorry for my poor english...
My problem is :
- I created a milestone "fixed date" A
- I created task B with predecessor milestone A
When I calculate planning the task B is not planned after milestone A.
Thanks
Posted : 20 Nov 2011 16H30
Hi,
This is clearly a bug.
Registered as ticket #476.
Posted : 20 Nov 2011 17H36