Ticket vs activities

2 Posts
2 Users
0 Reactions
1,527 Views
 BILA
(@lsigroup)
Posts: 304
Contributor
Topic starter
 
[#6607]

Hi,

I would like to avoid using activities but only tickets. It is more convenient to manage people work by using Diary view. But how to proceed if the ticket last more than 1 day ?

As only one date is available in ticket (planned date), it will be displayed in the diary at this date. But how to make it appear on a period?

Thanks for your help.


 
Posted : 03 Apr 2020 14H30
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

As ticvket is not "planable" it cannot be displayed on several days.
It is only displayed on target day.
Only planable items such as activities can be displayed on several days.


 
Posted : 05 Apr 2020 16H05