Use of Affectations in planing calculation

2 Posts
2 Utilisateurs
0 Reactions
3,163 Vu
(@bsimon)
Posts: 6
Active Member
Début du sujet
 
[#2641]

I have :
- a ressource affected at 50% on a projet,
- an unique activity in th eproject (with the ressource at 100% and a effort of 2 days)
when I launch the planing calculation with : the activity is planned on 2 days and not 4 ==> It seems that affectation is not taken into account in planing calculation.
(I use version 5.0.3)


 
Posté : 7 Oct PM 22:1010
(@babynus)
Posts: 14952
Membre Admin
 

Affectation rate is taken into account... on a weekly basis.
It is considered that if a resource is affected 50% on P1 and 50% on P2, it should not work half days on each, but half weeks on each.
It means planning will set 2,5 days on P1 then 2,5 daus on P2.
Try and change your effort to 5, you'll see what I mean.

If you want a daily basis restriction, use assignement rate at 50%.


 
Posté : 9 Oct AM 11:1010