Forum

validated work on p...
 
Notifications
Retirer tout

validated work on project level

3 Posts
3 Utilisateurs
0 Reactions
4,437 Vu
(@chris_1784997064)
Posts: 50
Active Member
Début du sujet
 
[#4969]

Hello all,

On project level the field validated work is greyed out.
The project is not handled/done/closed
Time is booked on activities, as you can see.

The question is:
Due to what actions will be this field greyed out, and cannot be edited anymore.
Can I reverse this, to edit the field later on again?

Thanks a lot.

Best regards


 
Posté : 14 Fév PM 13:022
(@richard-pare)
Posts: 165
Active Member
 

Have you set parameter "Consolidate validated work & cost" with "Always" or "Only is set"?

If so, this is the normal behaviour with this functionality.

For edited this field again (at project level), you must erase all validated work value for all sub-elements.

Resetting the parameter "Consolidate validated work & cost" to "Never" is not enough.


 
Posté : 14 Fév PM 16:022
(@babynus)
Posts: 14952
Membre Admin
 

Validated work is lock when it is consolidated from sub-items.
If you wish to be able to manually enter validated at each level, just change consolidation mode of validated work (on global parameters screen)


 
Posté : 14 Fév PM 22:022
Share:
Retour en haut