Version 4.5.4: problem with planning

6 Posts
2 Users
0 Reactions
3,712 Views
(@igio80)
Posts: 30
Active Member
Topic starter
 
[#2167]

Hi guys.
I downloaded version 4.5.4 and I'm using for the first time this software.
Probably something wrong because I can not get automatically update the planning (Gantt) when I finish a task before the scheduled date.
In practice, if the first task is scheduled between January 1 to 10 and the second connected (Successor Element) from 11 January, when I finish (closed) the first task on January 5, I expect that the second task automatically starts from 6 and instead continues from the day 11 ... why? I assigned the task to a resource and set the dates requested. Thank You.


 
Posted : 23 Jan 2015 17H14
(@babynus)
Posts: 14952
Member Admin
 

Did you update left work on first task so that there is no left work ?
Can you create an example on demo ?


 
Posted : 23 Jan 2015 21H39
(@igio80)
Posts: 30
Active Member
Topic starter
 

Resolved! I must update left work. Thank you very much.


 
Posted : 26 Jan 2015 11H46
(@igio80)
Posts: 30
Active Member
Topic starter
 

How can I edit planned in my activity? It's disable for editing.


 
Posted : 08 May 2015 13H21
(@babynus)
Posts: 14952
Member Admin
 

You cannot.
Planned is calculated : planned = real + left.

RTFM


 
Posted : 08 May 2015 13H47
(@babynus)
Posts: 14952
Member Admin
 

For information, due to possible common confusion, in V5, "Planned work" will be renamed "Reassessed work"


 
Posted : 08 May 2015 15H12