Hi guys.
I downloaded version 4.5.4 and I'm using for the first time this software.
Probably something wrong because I can not get automatically update the planning (Gantt) when I finish a task before the scheduled date.
In practice, if the first task is scheduled between January 1 to 10 and the second connected (Successor Element) from 11 January, when I finish (closed) the first task on January 5, I expect that the second task automatically starts from 6 and instead continues from the day 11 ... why? I assigned the task to a resource and set the dates requested. Thank You.
Did you update left work on first task so that there is no left work ?
Can you create an example on demo ?
Resolved! I must update left work. Thank you very much.
How can I edit planned in my activity? It's disable for editing.
You cannot.
Planned is calculated : planned = real + left.
RTFM
For information, due to possible common confusion, in V5, "Planned work" will be renamed "Reassessed work"