Wrong manipulation with plannification ?

6 Posts
2 Users
0 Reactions
3,025 Views
(@jonathan02500)
Posts: 21
Active Member
Topic starter
 
[#3420]

Hello all ,
I have a question concerning plannification.
I want to start my project tomorrow,
So i put into my requested date the date of tomorrow but each time the software chnange the planned date at today.
I don't know why, someone can help me please ?

Have a good day.


 
Posted : 25 May 2016 17H33
babynus
(@babynus)
Posts: 14953
Main Contributor Admin
 

The requested date is just informative : the date the customer requested (his Christmas wish list)
The date that should be taken into account is the validated start date. But it is not a constraint to planning calculation.
You need to set a real constraint to planning calculation. For instance, add a "fixed" milestone starting on tomorrow, then make your first task of project start after the milstone (add dependencing link).


 
Posted : 26 May 2016 10H31
(@jonathan02500)
Posts: 21
Active Member
Topic starter
 

Hello
Thank you for you reply, i understand a little more now 🙂

When i want to plannify my ressource i don't understand but when i put 5 days on my "charge" (#1 in my screenshoot) and i modify the assignation of the ressource and fill 5 days (#2 in my screenshoot) the planning is modify and as you can see (#3 in my screenshoot) there is 7 days of work, howerver i want 5 ?
Can you help me please 🙂

And can you tell how the value in yellow is calculate please in my second screenshoot.

Have a good day 🙂


 
Posted : 26 May 2016 11H53
babynus
(@babynus)
Posts: 14953
Main Contributor Admin
 

Have a look at report "planning per resource/project/activity" in "planning" report category.
You'll see exacly what the resource does or is planned to do on the oeriod.
Maybe he is busy on another project.


 
Posted : 26 May 2016 21H42
(@jonathan02500)
Posts: 21
Active Member
Topic starter
 

Hello,Thank for your reply,
Thanks to you i learn a lot of things about the software.

However my problem isn't solve yet.
As you can see in attachment my ressource isn't use in other project so i don't know why the capacity is 6days :'(

Have a good day


 
Posted : 27 May 2016 11H34
babynus
(@babynus)
Posts: 14953
Main Contributor Admin
 

Your resource is attending a meeting, on friday, taking 0,06 days of resource availability.
So this resouce cannot work 5 full days on the task you expect him to work. The 5 work days (as workload) will be planned in more that 5 dayxs (exactly 5,06 days, being reported as 6 day (duration is not rounded but ceilled)


 
Posted : 30 May 2016 23H40