Just select the sub-project in the project filter (a sub-project is a project).
We don't see the administrative projects in the list
You should see them only if you are affected to them.
Sorry, it's not for sub-project but for activities
How can I obtain the time spent by user for just one activitie ?
I didn't find report with this possibility
Yannick
Several reports will help you :
- Work => Detailed work per resource
- Planning => Monthly planning resource/project/activity
Or easier : just access the activity.