Add filter for reports Work

6 Posts
2 Utilisateurs
0 Reactions
3,625 Vu
(@002514)
Posts: 68
Active Member
Début du sujet
 
[#1597]

Hi Babynus

I would like to have the possibility to filter by sub-project in work Category reports

Do you think that it's possible ?

thanks
Yannick


 
Posté : 24 Jan PM 19:011
(@babynus)
Posts: 14952
Membre Admin
 

Just select the sub-project in the project filter (a sub-project is a project).


 
Posté : 24 Jan PM 19:011
(@002514)
Posts: 68
Active Member
Début du sujet
 

We don't see the administrative projects in the list


 
Posté : 24 Jan PM 20:011
(@babynus)
Posts: 14952
Membre Admin
 

You should see them only if you are affected to them.


 
Posté : 24 Jan PM 21:011
(@002514)
Posts: 68
Active Member
Début du sujet
 

Sorry, it's not for sub-project but for activities
How can I obtain the time spent by user for just one activitie ?

I didn't find report with this possibility

Yannick


 
Posté : 25 Jan AM 11:011
(@babynus)
Posts: 14952
Membre Admin
 

Several reports will help you :
- Work => Detailed work per resource
- Planning => Monthly planning resource/project/activity

Or easier : just access the activity.
You'll have real work in the assignment.


 
Posté : 25 Jan PM 16:011