Hi,
Currently settings for maxProjectsToDisplay affect both - planning and resource planning. This is not very convenient. For example I do not want to load all our projects into planning but I want to have all projects in resource planning to see resources workload. Is it possible to separate settings for this 2 screens?
Regards,
Evgueni
In fact this parameter should not influence resource planning.
I'll have a look.
Fixed in V2.4
Thanks!