Hi,
Currently settings for maxProjectsToDisplay affect both - planning and resource planning. This is not very convenient. For example I do not want to load all our projects into planning but I want to have all projects in resource planning to see resources workload. Is it possible to separate settings for this 2 screens?
Regards,
Evgueni


 
Posted : 09 Jul 2012 13H38
(@babynus)
Posts: 14952
Member Admin
 

In fact this parameter should not influence resource planning.
I'll have a look.


 
Posted : 09 Jul 2012 13H59
(@babynus)
Posts: 14952
Member Admin
 

Fixed in V2.4


 
Posted : 09 Jul 2012 14H09
Evgueni Kolossov
(@ekolossov)
Posts: 566
Contributor
Topic starter
 

Thanks!


 
Posted : 09 Jul 2012 14H35