DEDIEU
(@jcde)
Posts: 104
Estimable Member
Début du sujet
 
[#1194]

Hello

I have 3 requests:

1) Closing a project with all activities
If activities are not close and the RAF is 0, close all automatically (so need a result write in result "closed by .... on ....")
Make same for the project 'canceled' state

2) When closing a project must clear the workplanned (a CDP may be set RAF to 0 but not have relaunched PLANNING. So we find ourselves with planned days that you can not delete.

3) In the reports add two checkboxes that allow to add information related to the project closed or canceled

Thank you


 
Posté : 05/06/2013 1:36 pm
(@babynus)
Posts: 14952
Membre Admin
 

1) Closing a project with all activities

V3.4 will bring similar feature : change for many items.
So it will be possible to select all non closed activities of a project and close then in one step, with display of result : it is important as closing may be prohibited by some rules (remaining work for instance).


 
Posté : 07/06/2013 8:27 pm
(@babynus)
Posts: 14952
Membre Admin
 

2) When closing a project must clear the workplanned (a CDP may be set RAF to 0 but not have relaunched PLANNING. So we find ourselves with planned days that you can not delete.

I thought this issue was fixed.
I'll have a look.


 
Posté : 07/06/2013 10:10 pm
(@babynus)
Posts: 14952
Membre Admin
 

3) In the reports add two checkboxes that allow to add information related to the project closed or canceled

Ticket #1101 recorded


 
Posté : 07/06/2013 10:11 pm
Share: