Activity fixed duration : can't change avancement planning view

4 Posts
2 Utilisateurs
0 Reactions
1,124 Vu
jmmbb
(@jmmbb)
Posts: 561
Contributor
Début du sujet
 
[#9294]

Hello,

with an activity set "fixed duration", charge set and no assignation, i can't change avacement value in planning view.
It work fine in activity view.
Let show screen capture :
From planning, avancement is locked
 

From activity, it's fine :
 

Regards,


 
Posté : 6 Fév PM 17:022
(@marylene)
Posts: 592
Membre Admin
 

Hello,

indeed, I reproduce and it is not normal
Ticket #8019 recorded


 
Posté : 7 Fév AM 11:022
jmmbb
(@jmmbb)
Posts: 561
Contributor
Début du sujet
 

The same way, being able to modify the avancement value directly in the right part of gantt (like description,...) will be usefull :
 


 
Posté : 7 Fév PM 16:022
(@marylene)
Posts: 592
Membre Admin
 

good idea ! I add it to the ticket!


 
Posté : 8 Fév PM 12:022