Activity fixed duration : can't change avancement planning view

4 Posts
2 Users
0 Reactions
1,154 Views
jmmbb
(@jmmbb)
Posts: 561
Contributor
Topic starter
 
[#9294]

Hello,

with an activity set "fixed duration", charge set and no assignation, i can't change avacement value in planning view.
It work fine in activity view.
Let show screen capture :
From planning, avancement is locked
 

From activity, it's fine :
 

Regards,


 
Posted : 06 Feb 2024 17H56
(@marylene)
Posts: 592
Contributor Admin
 

Hello,

indeed, I reproduce and it is not normal
Ticket #8019 recorded


 
Posted : 07 Feb 2024 11H29
jmmbb
(@jmmbb)
Posts: 561
Contributor
Topic starter
 

The same way, being able to modify the avancement value directly in the right part of gantt (like description,...) will be usefull :
 


 
Posted : 07 Feb 2024 16H17
(@marylene)
Posts: 592
Contributor Admin
 

good idea ! I add it to the ticket!


 
Posted : 08 Feb 2024 12H12