Activity fixed duration : can't change avancement planning view
(@jmmbb)
Posts: 561
Contributor
Hello,
with an activity set "fixed duration", charge set and no assignation, i can't change avacement value in planning view.
It work fine in activity view.
Let show screen capture :
From planning, avancement is locked
From activity, it's fine :
Regards,
Posted : 06 Feb 2024 17H56
(@marylene)
Posts: 592
Contributor Admin
Hello,
indeed, I reproduce and it is not normal
Ticket #8019 recorded
Posted : 07 Feb 2024 11H29
(@jmmbb)
Posts: 561
Contributor
The same way, being able to modify the avancement value directly in the right part of gantt (like description,...) will be usefull :
Posted : 07 Feb 2024 16H17
(@marylene)
Posts: 592
Contributor Admin
good idea ! I add it to the ticket!
Posted : 08 Feb 2024 12H12