Hi,
I have project, subproject.
Only Subproject have activity.
I try to prioritize activity from all of the project and other project, but it does not work.
All activity have same characteristics, and a priority to 500.
I put 400 on this activity, no change on the diary.
Il put valid and request date to the date of the work.
I can't change WBS project and activity…
Do I miss something ?
Thanks.
I put 400 on this activity, no change on the diary.
You mist recalculate planning to see chages
Il put valid and request date to the date of the work.
This have no impact on planning
I can't change WBS project and activity…
You can : just move tasks /projects in Gantt view.
Hi,
I have calculate the planning before post, il forget to write it.
Another solution ?
If I move task or project, all the other activity will be impacted. I don't want this.
Thanks.
Can you please try and repriduce your use case on Demo ?
Hi,
I've created Projects
ATB 1
- ATB 1-1
-- ATB 1-1-1
ATB 2
- ATB 2-1
-- ATB 2-1-1
As Supervisor, ATB 1 and ATB 2 are sub projects of JES, it is not with manager.
As manager, i want to create activity to Dev ATB on ATB 1-1-1, but it don't appear on the list.
Tell me, I continue after…
Thanks.
Users are "superviseur" and "gestionnaire"...
Please be more precise.
I can see
ATB 1
- ATB 1-1
-- ATB 1-1-1
ATB 2
- ATB 2-1
-- ATB 2-1-1
Gestionnaire is allocated as Project Leader to ATB 1 and ATB 1-1 (no use as prfile is inherited from parent) and ATB 1-1-1.
Gestionnaire is allocated as Project Leader to ATB 2 and ATB 2-1 (no use as prfile is inherited from parent) and ATB 2-1-1
Dev ATB is allocated as Projct Member to ATB 1-1-1 and to ATB 2-1-1
ATB 1 and ATB 2 are NOT sub projects of JES, The are at root os structure (wbs 84 and 85).
i want to create activity to Dev ATB on ATB 1-1-1
The is no activity on ATB-1-1-1...
Connected as admin, I just created Activity "New activity" on project ATB 1-1-1, then assigned Dev ATB : all works fine.
Connected as Gestionnaire, I just created Activity "New activity as gestionnaire" on project ATB 1-1-1, then assigned Dev ATB : all works fine.
As supervisor, you cannot create activity nor assign resource : supervisseur only has "read-only' rights.
Please explain what you try to do, expected result and what you get.
Please post screenshot to explain.