If the start and end dates are blank, replace with start and end date of project

2 Posts
2 Users
0 Reactions
2,267 Views
(@narayanaras)
Posts: 150
Active Member
Topic starter
 
[#5108]

The Gantt chart shows the project between the Display from and Display to dates.

If the Display from field is left blank, display the project from its own start date.
Similarly, if the Display to field is left blank, display the project till its end.


 
Posted : 27 Apr 2018 12H36
(@babynus)
Posts: 14952
Member Admin
 

If the Display from field is left blank, display the project from its own start date.

As of today, current date is taken into account
This could be an option to display from project start date...
Request recorded as ticket #3353

Similarly, if the Display to field is left blank, display the project till its end.

This is already default behavior


 
Posted : 27 Apr 2018 13H18