[SOLVED] Cost and Works left work error

3 Posts
2 Users
0 Reactions
1,828 Views
(@karl-binet)
Posts: 128
Active Member
Topic starter
 
[#7521]

Hi,

V9.1.3

In a activity I have incorrect value in Cost and Work Assigned Work 137h - Real 41.25 total 95.75h but left works shows 115H

I'm having this issue in other project/activities.

I did he Fix Issues in consistency checks, did not change anythings

Any hint on how to solved this issue 

Regards


 
Posted : 03 May 2021 17H10
(@babynus)
Posts: 14952
Member Admin
 

IT is not an error.
It is just that resource changed Left work to point out he will not finish on time.
Left is not always Assigned - Real (otherwise we yould not need reassessed)


 
Posted : 04 May 2021 20H27
(@karl-binet)
Posts: 128
Active Member
Topic starter
 

Great, i understand, i looked at all the activities attach to this one and i found an activity that hours were manually added.

Thanks


 
Posted : 05 May 2021 21H30