Hi,

V9.1.3

In a activity I have incorrect value in Cost and Work Assigned Work 137h - Real 41.25 total 95.75h but left works shows 115H

I'm having this issue in other project/activities.

I did he Fix Issues in consistency checks, did not change anythings

Any hint on how to solved this issue 

Regards


 
Posté : 03/05/2021 5:10 pm
(@babynus)
Posts: 14952
Membre Admin
 

IT is not an error.
It is just that resource changed Left work to point out he will not finish on time.
Left is not always Assigned - Real (otherwise we yould not need reassessed)


 
Posté : 04/05/2021 8:27 pm
(@karl-binet)
Posts: 128
Reputable Member
Début du sujet
 

Great, i understand, i looked at all the activities attach to this one and i found an activity that hours were manually added.

Thanks


 
Posté : 05/05/2021 9:30 pm