Hi,
V9.1.3
In a activity I have incorrect value in Cost and Work Assigned Work 137h - Real 41.25 total 95.75h but left works shows 115H
I'm having this issue in other project/activities.
I did he Fix Issues in consistency checks, did not change anythings
Any hint on how to solved this issue
Regards
IT is not an error.
It is just that resource changed Left work to point out he will not finish on time.
Left is not always Assigned - Real (otherwise we yould not need reassessed)
Great, i understand, i looked at all the activities attach to this one and i found an activity that hours were manually added.
Thanks