[SOLVED] Planning four task of 0,25 day in one day

5 Posts
3 Users
0 Reactions
1,775 Views
(@nhedhili)
Posts: 79
Active Member
Topic starter
 
[#7744]

Hello 
we need to plan four tasks each of 0,25 day for one ressource l in one day.
assignation of the ressource  is 0,25 for each task with 100%
planning mode is regular between two dates 
ressource capacity = 1 
We tried all the combinations only three tasks can be planned , I tried one task of 0,5 day and two tasks of 0,25 day assignation it only can schedule 0,75 day of assignation whatever the combination.

Thanks  for your help and assistance 


 
Posted : 03 Sep 2021 20H35
Flou
 Flou
(@flou)
Posts: 253
Active Member
 

Hello,

What is the rate of your resource affection on your project ? 
Is it possible that your resource is assigned in parallel to another activity of another project?


 
Posted : 07 Sep 2021 13H19
(@nhedhili)
Posts: 79
Active Member
Topic starter
 

Hello
the rate is 100% and the ressource is not assigned to other tasks or porjects.
if I affect them to two tasks 0f 0,5 day it works fine , but if I affect them same period in four tasksof 0.25 day it ony takes into consideration onl three tasks of 0.25 day in the same day which is a strange behaviour


 
Posted : 07 Sep 2021 17H39
(@babynus)
Posts: 14952
Member Admin
 

Hi,

I could not reproduce.?
Tested on Demo, you can have a look to project ProjeqtorTest01, with brand new resource ProjeqtorTest01.
Works really as expected.


 
Posted : 09 Sep 2021 11H21
(@nhedhili)
Posts: 79
Active Member
Topic starter
 

issue is solved , there was a task in another project not included in the calculation , doing calculculation fior all the prject soved fixed the planning.
thank you for your assistance


 
Posted : 10 Sep 2021 21H43