Good Morning,
While using projeqtor on the timesheet view i get my real time on an activity "twice", on as "développeur" and the other one as "chef de projet"
2 ressources are working on that activty (id 165 and 191)
When i check on data base for these ressources i've got the same assignement ID for the same Activity and i don't know how it end up likes that.
Another thing is that when i go back into Activity screen and i update the assignement the ID are differents for the profil "Développeur" and "Chef de projet" so why are they equals in DataBase?
Developpeur A ssignement :
Chef de projet Assignement :
thanks for helping
As pictures are not rendering on my previous post here's a re-upload
While using projeqtor on the timesheet view i get my real time on an activity "twice", on as "développeur" and the other one as "chef de projet"
2 ressources are working on that activty (id 165 and 191)
When i check on data base for these ressources i've got the same assignement ID for the same Activity and i don't know how it end up likes that.
Another thing is that when i go back into Activity screen and i update the assignement the ID are differents for the profil "Développeur" and "Chef de projet" so why are they equals in DataBase?
Developpeur A ssignement :
Chef de projet Assignement :
oops,
with developer's view i've got "aucune modification à sauver pour l'élément Assignation #4147 "
Hi,
It is possible if resources entered work on assignement of a pool to which they belong.
The idAssignement refers to the assignement of the pool.
It may also possible (I think) if work is entered through Ticket.
Does the work lines have non null idWorkElement ?
Hello,
Work isn't enter through Ticket (we use timesheet screen only). Also in DataBase every line of work got Null idWorkElement
We get this "Bug" once again yesterday and i think it occur when a ressource input time for another ressource.
For example Ressource A input time for Ressource B From Monday to Friday, 8 hours per day on the same activity. Ressource B will have it's time well input but ressource A will also get it so when it want to input time for his own activity it will get [Ressource A's activity + Ressource B's Activity] speaking of time spent
after upgrade every thing is fine