[SOLVED] sub project with rest but without rest on activities or tickets???

5 Posts
3 Users
0 Reactions
2,428 Views
(@durou-c)
Posts: 468
Contributor
Topic starter
 
[#5536]

I have a problem with my database.

I have a subproject with rest to do while everything is closed, no tickets, activities or other have hours of rest to do.
How to force the rest to make the sub project to 0 to close it


 
Posted : 08 Nov 2018 12H14
Gautier
(@gautier)
Posts: 207
Active Member Admin Registered
 

Hello,

If you request is : "item can't be 'done' with left work "
there is a parameter in : Parameters -> list of types -> projects types


 
Posted : 08 Nov 2018 13H44
(@durou-c)
Posts: 468
Contributor
Topic starter
 

no the message is : Unable to close an element with left work

on this sub-project, it's left rest work 67.5h. but all of tickects and activities are closed and all have rest at 0h.

I don't understand why the rest of sub project is 67.5h ???


 
Posted : 08 Nov 2018 14H22
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

You possibly have items (meeting, test session or else) with left work.
Try and set "can force close" on specific access rights for the given profile.
You 'll then be able to close and this will force left to zero.


 
Posted : 08 Nov 2018 17H09
(@durou-c)
Posts: 468
Contributor
Topic starter
 

tks, it's work and I could closed it


 
Posted : 08 Nov 2018 17H33