I have a problem with my database.

I have a subproject with rest to do while everything is closed, no tickets, activities or other have hours of rest to do.
How to force the rest to make the sub project to 0 to close it


 
Posté : 8 Nov PM 12:1111
Gautier
(@gautier)
Posts: 207
Membre Admin Registered
 

Hello,

If you request is : "item can't be 'done' with left work "
there is a parameter in : Parameters -> list of types -> projects types


 
Posté : 8 Nov PM 13:1111
(@durou-c)
Posts: 468
Contributor
Début du sujet
 

no the message is : Unable to close an element with left work

on this sub-project, it's left rest work 67.5h. but all of tickects and activities are closed and all have rest at 0h.

I don't understand why the rest of sub project is 67.5h ???


 
Posté : 8 Nov PM 14:1111
(@babynus)
Posts: 14952
Membre Admin
 

You possibly have items (meeting, test session or else) with left work.
Try and set "can force close" on specific access rights for the given profile.
You 'll then be able to close and this will force left to zero.


 
Posté : 8 Nov PM 17:1111
(@durou-c)
Posts: 468
Contributor
Début du sujet
 

tks, it's work and I could closed it


 