[SOLVED] Wrong total for assigned and reassessed ?

6 Posts
2 Users
0 Reactions
3,229 Views
(@papjul)
Posts: 143
Active Member
Topic starter
 
[#2697]

Hello,

I don't know if it's an issue or if you have an explanation for this but total for assigned and reassessed should be 171 d (on screenshot), why is it 175 d and 174,5d?

Thank you,


 
Posted : 03 Nov 2015 11H56
(@babynus)
Posts: 14952
Member Admin
 

Assigned can be different from validated.
I don't see all lines, so cannot sum up all assigned.
For re-assessed, it is always real+left : so calculation seems correct.


 
Posted : 03 Nov 2015 12H51
(@papjul)
Posts: 143
Active Member
Topic starter
 

OK for reassessed I didn't know what it was.
All lines are here, what are you missing? What do I need to screenshot?


 
Posted : 03 Nov 2015 13H38
(@papjul)
Posts: 143
Active Member
Topic starter
 

We deleted all assignments and 4 days remained on the root project.


 
Posted : 03 Nov 2015 13H39
(@babynus)
Posts: 14952
Member Admin
 

1) First I did not see that last lines are not summed up on the parent task above (grey line). If is surely because they are directly under the project.

2) If after deletion you still have assigned work, I may be because you have a closed activity. Try and display activiites with "show closed" checkbox checked.


 
Posted : 03 Nov 2015 20H30
(@papjul)
Posts: 143
Active Member
Topic starter
 

Indeed it was due to a closed activity!
Thank you!


 
Posted : 04 Nov 2015 11H18