Assigned can be different from validated.
I don't see all lines, so cannot sum up all assigned.
For re-assessed, it is always real+left : so calculation seems correct.
OK for reassessed I didn't know what it was.
All lines are here, what are you missing? What do I need to screenshot?
We deleted all assignments and 4 days remained on the root project.
1) First I did not see that last lines are not summed up on the parent task above (grey line). If is surely because they are directly under the project.
2) If after deletion you still have assigned work, I may be because you have a closed activity. Try and display activiites with "show closed" checkbox checked.
Indeed it was due to a closed activity!
Thank you!