Hello all,
I created some projects and attached some activities to each of it.
I created resources that are attached to project and activities.
When I go to the screen to declare days charged on projects ("imputations" in french), some of them are not visible or available.
If someone already fixed this kind of issue, or if some ideas, please tell me.
Hi,
You should check on specific acces "limit visibility on resources" how rights are specified by profil. Then have a look on "Access to resource data - Acces on timesheet for resource" to choose your best option.
Thank you for your feedback.
Nevertheless, I didn't specify any specific acces to resources.
I created all of them by the same way, without any profil or right acces management.
Hello,
Please, check the settings with the screen specific access into 1st, 12th and 13th section
I transmitted your answer to the IT teams to check these screen, because they're not visible by my side.
ok, it's fixed by giving me the rights on all resources.
But I still don't understand why we had to modify these right while they're all on project on wich I'm manager (taking into account that i'm also "supervisor" in ProjeQtOr), and all resources have been defined in the same time by the same method.
Glad this is resolved.
The designated manager on project screen into the field called " Manager" is a person who gets already a profile with rights, whatever it is. This profil allocated to the resource can be setted up and named "Manager" (nothing prohibiting it). Here I think where the purpose lied.