some resources are not availables in the page to declare days charged/realized

7 Posts
2 Utilisateurs
0 Reactions
1,641 Vu
(@sgu_d2m_enineering)
Posts: 5
Active Member
Début du sujet
 
[#9765]

Hello all,

I created some projects and attached some activities to each of it.
I created resources that are attached to project and activities.
When I go to the screen to declare days charged on projects ("imputations" in french), some of them are not visible or available.

If someone already fixed this kind of issue, or if some ideas, please tell me.


 
Posté : 27/02/2025 6:05 pm
(@alain-fourastie)
Posts: 366
Membre Moderator
 

Hi,
You should check on specific acces "limit visibility on resources" how rights are specified by profil. Then have a look on  "Access to resource data - Acces on timesheet for resource" to choose your best option. 


 
Posté : 27/02/2025 6:52 pm
(@sgu_d2m_enineering)
Posts: 5
Active Member
Début du sujet
 

Thank you for your feedback.
Nevertheless, I didn't specify any specific acces to resources.
I created all of them by the same way, without any profil or right acces management.


 
Posté : 27/02/2025 7:01 pm
(@alain-fourastie)
Posts: 366
Membre Moderator
 

Hello,

Please, check the settings with the screen specific access into 1st, 12th and 13th section


 
Posté : 28/02/2025 11:13 am
(@sgu_d2m_enineering)
Posts: 5
Active Member
Début du sujet
 

I transmitted your answer to the IT teams to check these screen, because they're not visible by my side.


 
Posté : 28/02/2025 11:37 am
(@sgu_d2m_enineering)
Posts: 5
Active Member
Début du sujet
 

ok, it's fixed by giving me the rights on all resources.
But I still don't understand why we had to modify these right while they're all on project on wich I'm manager (taking into account that i'm also "supervisor" in ProjeQtOr), and all resources have been defined in the same time by the same method.


 
Posté : 28/02/2025 1:08 pm
(@alain-fourastie)
Posts: 366
Membre Moderator
 

Glad this is resolved.
The designated manager on project screen into the field called " Manager" is a person who gets already a profile with rights, whatever it is. This profil allocated to the resource can be setted up and named "Manager" (nothing prohibiting it). Here I think where the purpose lied.


 
Posté : 28/02/2025 1:52 pm