Hi all,
if a milestone is moved to handled/close/done the planning date is not adjusted to the "real" date and the milestone stays on the planned date in the GANTT View
We think this is a new issue on V8.2.2
Could you confirm that?
BR
Posté : 02/10/2019 4:13 pm
I confirm there is an issue, but not linked to V8.2.
It exists on V8.0.
In fact, if real end date is set on the milestone (from done date), you must save twice to have planned date updated.
And then, replaning erases it to wrong value.
Issue recorded as Ticket #4239