The critical path does not show the entire path

4 Posts
2 Users
0 Reactions
2,386 Views
(@narayanaras)
Posts: 150
Active Member
Topic starter
 
[#5116]

As shown in the following screenshot, the critical path does not highlight all the elements.

In this case, Task-1 should have been marked as critical (red line through it).


 
Posted : 30 Apr 2018 10H13
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Not sure it is (and not sure it's not).
It this task has no predecessor, it may not be on critical path.

We should see start of project to be sure.


 
Posted : 30 Apr 2018 13H38
(@narayanaras)
Posts: 150
Active Member
Topic starter
 

Well, all the tasks touching the left are at the start of the project (they are in ASAP mode).
But the MCP should be shown throughout the project, including the starting task.
Why does it not mark the task at the starting of the project?


 
Posted : 30 Apr 2018 17H07
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

OK.
I have an idea.
Maybe it's an issue introduced when trying to fiw another issue on critical patch (as late as possible always on critical path)
Ticket #3359 recorded


 
Posted : 30 Apr 2018 17H17