[v6.0.1 acceptance review] - S curve

4 Posts
2 Users
0 Reactions
2,469 Views
(@verges)
Posts: 85
Active Member
Topic starter
 
[#4155]

We have an issue on a project about the display of "reassessed" workload.

On this project (cf. capture attached, the "reaseessed" workload is : 105.75).

The S curve displays the "assigned" workload rather than the "reassessed" workload (cf. capture attached). There is an issue on the "Coût réel du travail effectué (prévu)" curve.

Thanks,

Regards,


 
Posted : 01 Mar 2017 20H30
(@babynus)
Posts: 14952
Member Admin
 

Hi,

Was the planning recalculated for the project ?

There may be a difference with reassessed work (on project) and S-curve :
- the reassessed work automatically takes into account actualized left work
- the S-curve takes into account work planned, day by day.
So if left work has been changed since last planning calculation, there will be a difference.


 
Posted : 02 Mar 2017 18H47
(@verges)
Posts: 85
Active Member
Topic starter
 

Yes we have recalculate the project:

Cf. this ticket : http://www.projeqtor.org/fr/forum-fr/2-submit-issues/8167-v6-0-1-acceptance-review-s-curve-validate-planning

to undertand better our issue.


 
Posted : 03 Mar 2017 21H05
(@babynus)
Posts: 14952
Member Admin
 

Hi,

I cannot see wource of issue, and it's difficult to analyse without reproducing.
What is weird is that S-Curve stops on April 10th, although it should continue up to April 19th (planned end date).
Could you provide us with an anomized dump of your database to let us analyse ? (contact le through mail)

NB : I don't understand why you refered to www.projeqtor.org/fr/forum-fr/2-submit-i...ve-validate-planningwww.projeqtor.org/fr/forum-fr/2-submit-i...ve-validate-planning. It deals with "budgeted cost of work scheduled" and current one deals with "Actual cost of work performed"


 
Posted : 04 Mar 2017 22H59