Activied planned for Mon&Tue just 4hours per day during 5 weeks - How can I create it ?

3 Posts
2 Users
0 Reactions
4,318 Views
Carlos Cattani
(@ccattani)
Posts: 27
Active Member
Topic starter
 
[#1246]

How can I create an activity planned to be delivered just during 4 hours on modays and tuesdays during 5 weeks ?

Regards

Carlos


 
Posted : 08 Jul 2013 18H51
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Hi,

There is no planning mode that will ensure this so specific planning.
Maybe with a planning mode 'regular in half days', for a task with 40 hours assigned, you'll get something apprimatively fitting.
The best way to get exactly what you expect is to directly enter the real work in the real work allocation screen for this task.


 
Posted : 08 Jul 2013 19H12
Carlos Cattani
(@ccattani)
Posts: 27
Active Member
Topic starter
 

I have a 3 days duration activity which in regular planning (as soon as possible) is planned correctly (3 days), but when I change the planning to Regular in Half Days, it remains with a 3 days duration instead of 6. I'm attaching the activity'ws configuration screen.


 
Posted : 16 Jul 2013 20H32