How can I create an activity planned to be delivered just during 4 hours on modays and tuesdays during 5 weeks ?

Regards

Carlos


 
Posté : 8 Juil PM 18:077
(@babynus)
Posts: 14952
Membre Admin
 

Hi,

There is no planning mode that will ensure this so specific planning.
Maybe with a planning mode 'regular in half days', for a task with 40 hours assigned, you'll get something apprimatively fitting.
The best way to get exactly what you expect is to directly enter the real work in the real work allocation screen for this task.


 
Posté : 8 Juil PM 19:077
Carlos Cattani
(@ccattani)
Posts: 27
Active Member
Début du sujet
 

I have a 3 days duration activity which in regular planning (as soon as possible) is planned correctly (3 days), but when I change the planning to Regular in Half Days, it remains with a 3 days duration instead of 6. I'm attaching the activity'ws configuration screen.


 