Confusion in Duration concept.

7 Posts
4 Users
0 Reactions
2,958 Views
(@chandrashekhar)
Posts: 275
Contributor
Topic starter
 
[#8221]

Hi Expert,

I can't understand about duration shown in planning. I have attached a screenshot. for reference. I am calculating duration=end date - start date.
i.e. for id=3 it is showing "164" (not considering both dates in the calculation)
      for id=17 it shows "20" (considering both start and end dates in the calculation).
      for id=286 it shows "1" (considering both start and end dates in the calculation).
      for id=1 it shows "-" 

Please give an understanding of my concern.

Note We have set off days (Saturday & Sunday).
I am using the xlsx file to find the duration (which is also attached for reference)
I have also attached global parameter screen for reference.

 


 
Posted : 22 Apr 2022 15H18
(@alain-fourastie)
Posts: 366
Active Member Moderator
 

HI,

Have you thought to replan the planning ?


 
Posted : 22 Apr 2022 16H32
(@chandrashekhar)
Posts: 275
Contributor
Topic starter
 

No, I was just observing progress %, planned work, left work, assigned work & I confused about duration column.


 
Posted : 22 Apr 2022 16H51
(@alain-fourastie)
Posts: 366
Active Member Moderator
 

You should, data could be refreshed.


 
Posted : 22 Apr 2022 18H56
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Duration is in "Open days" not in "Calendar days".
It removed all off days (week-ends and off days in default calendar)


 
Posted : 24 Apr 2022 15H05
(@chandrashekhar)
Posts: 275
Contributor
Topic starter
 

Thanks, I know that duration is calculated using open day only & I am reaching near to solution but here in our Company it is only second and fourth Saturday off. Can We set the calendar in that way? If I can do so It will get exactness in duration.


 
Posted : 25 Apr 2022 10H17
(@marylene)
Posts: 592
Contributor Admin
 

Hello !

To be able to do this, you must declare Saturday and Sunday as working days in the global parameters in the Work time tab, working days section.
Then on the calendars concerned you will be able to determine throughout the year which Saturdays and Sundays are not worked.
(yes yes, by hand 🙂


 
Posted : 25 Apr 2022 11H18