[#2909]

what is the difference between the green / purple and red bar ...??


 
Posted : 14 Jan 2016 0H26
(@babynus)
Posts: 14952
Member Admin
 

Green : Planned end date Validated end date (late)
Purple : All left work could not be planned (for instance resource has 5 left days but leaves project in 2 days....)


 