what is the difference between the green / purple and red bar ...??
Posté : 14 Jan AM 00:011
Green : Planned end date Validated end date (late)
Purple : All left work could not be planned (for instance resource has 5 left days but leaves project in 2 days....)
Posté : 14 Jan AM 10:011