Is it possible to move all dates (of activities,..) just by moving the dates of PROJECT?

2 Posts
2 Users
0 Reactions
3,420 Views
(@lutror)
Posts: 17
Active Member
Topic starter
 
[#1392]

I've copied a project with these activities and programming (dates). Is it possible to move all dates (of activities, milestones ..) automatically, just by moving the dates of the PROJECT?


 
Posted : 23 Sep 2013 13H44
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

No, not possible for "requested" and "validated" dates.
For planned date : a new planning calculation should do the job.


 
Posted : 24 Sep 2013 12H33