Link between tasks
 
Notifications
Clear all

Link between tasks

2 Posts
2 Users
0 Reactions
3,139 Views
(@pyhalleux)
Posts: 9
Active Member
Topic starter
 
[#3456]

I would like to link activities between them so that the second task starts when the first one is finished.
This does not work as I expect. See attachment 1. Does someone know why ?

Thank you for your answers.

Pierre-Yves


 
Posted : 10 Jun 2016 19H15
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

It is because your tasks are planned "as soon as possible" without assigned work.
This planning mode expects to have some assigned work.


 
Posted : 12 Jun 2016 14H29