Welcome to ProjeQtOr new Forum. We migrated old forum to the new website.
You will find all your posts here, with your usual account.
Just one point : you’ll have to reinitialize your password. Use “Lost password” feature.
Hi,
I need some help with meeting planning and the vision in the Charging screen.
In the attachement, we can see a meeting planned on the 31/01/2018.
In the charging screen, this meeting is planned the 15/01/2018.
What parameter should i modify to have the correct date in the charging screen ?
Thank's for your help
Possibly just recalculating the planing for the project is needed.
If issue persits after re-planning, check dependencies : a prédecessor on meeting or on parent activity may force move of meeting.
