Pb with an acitivity not planned

2 Posts
2 Users
0 Reactions
2,741 Views
(@noisette)
Posts: 24
Active Member
Topic starter
 
[#3983]

Dear all,

I have planned an activity from january, 2nd to december, 29th, with one ressource (50 hours).
This activity is a long-term one with few daily work (about 1 hr / day).
I planed this activity as "fixed duration".
The ressource has spent 3 hrs since January, 2nd.

BUT ProjeQtor has planed no task, and the real column said that the activity is over (finished).. and so the avancement is 100%.
you could see my pb in the screen capture I post with?
All the best
Christophe


 
Posted : 04 Jan 2017 16H35
babynus
(@babynus)
Posts: 14953
Main Contributor Admin
 

You have no left work.
Left work should be 36.5 hours.

NB : in your case, you should consider using planning mode "regular beetwen dates", which is designed exactly for your use case.


 
Posted : 06 Jan 2017 12H15