Dear all,
I have planned an activity from january, 2nd to december, 29th, with one ressource (50 hours).
This activity is a long-term one with few daily work (about 1 hr / day).
I planed this activity as "fixed duration".
The ressource has spent 3 hrs since January, 2nd.
BUT ProjeQtor has planed no task, and the real column said that the activity is over (finished).. and so the avancement is 100%.
you could see my pb in the screen capture I post with?
All the best
Christophe
You have no left work.
Left work should be 36.5 hours.
NB : in your case, you should consider using planning mode "regular beetwen dates", which is designed exactly for your use case.