Problem with imputations

4 Posts
2 Users
0 Reactions
1,613 Views
 BILA
(@lsigroup)
Posts: 304
Contributor
Topic starter
 
[#6243]

Hi,

We are currently having an issue, here's the situation :
We have a collegue who badly entered his hours on an activity (he entered multiple days) this cause the entire planning (every next acitivtys) to be shifted because of this bad imputation.
This is very blocking for us

Regards


 
Posted : 16 Sep 2019 12H38
(@babynus)
Posts: 14952
Member Admin
 

Sorry, I don't understand what is blocking.
If input is incorrect, just fix the input...


 
Posted : 16 Sep 2019 13H54
 BILA
(@lsigroup)
Posts: 304
Contributor
Topic starter
 

Because of the bad imputation my collegue entered,
The real time on this imputation is now 35,00 hours instead of 7
When whe are using the planning calculator the planified date changes because of that (in the example : 24/09/2019)

As you can see on the screenshot, we are unable to modify these values neither on the activity nor on the imputation.

Sorry if i'm not explaining very well, I'm doing my best but I'm not sure to understand everything either ...


 
Posted : 16 Sep 2019 19H18
(@babynus)
Posts: 14952
Member Admin
 

Issue on planning is due to left 49h work.
You can set this to zero on activity screen.
No more work will need to be replaned so planned end date will be real end date, which is the laste date of input of work in Timesheet.

You must change real work on Timesheet screen.
If it is lock, it should be because Week is submitted or validated. Unvalidate / unsubmit the week to change data.


 
Posted : 18 Sep 2019 20H00