Progress 100%?
 
Notifications
Clear all

Progress 100%?

2 Posts
2 Users
0 Reactions
2,816 Views
(@pavilonsxx)
Posts: 58
Active Member
Topic starter
 
[#2738]

Hi everyone!
I have one question about the progress of the project. My project has two jobs, job one time 10 days, job 2 times 20 days. At job 1, I just enter the result 2 days in real work item allocation. That is my first job unfinished. But when I see the current progress is 100% progress. Thanks to everyone explaining help me?


 
Posted : 17 Nov 2015 6H46
(@babynus)
Posts: 14952
Member Admin
 

Most likely you did not define work but only durations.

Progress calculation is based on Work.
If it sais progress = 100%, it means you have no left work.
Progress = Real Work / (Real Work + Left Work)


 