Hi everyone!
I have one question about the progress of the project. My project has two jobs, job one time 10 days, job 2 times 20 days. At job 1, I just enter the result 2 days in real work item allocation. That is my first job unfinished. But when I see the current progress is 100% progress. Thanks to everyone explaining help me?
Most likely you did not define work but only durations.
Progress calculation is based on Work.
If it sais progress = 100%, it means you have no left work.
Progress = Real Work / (Real Work + Left Work)