Planned days come from Planning Calculation, that you can run on Planning Gantt view.
Planning takes into account all constraints about Resource capacity, affectation rate, work assigned, assignment rate, planning mode for tasks, depedencies between tasks and priorities.
Thank you I guess I have undertood how it work