Hello,
In the menu “report, planning, work plan per month” (see attached display copy), how is calculated (or where do it come from) the planned days ? : see data surrounded in red in the attached display copy.
Thank by advance for any precision
Eric


 
Posté : 17 Fév AM 01:022
(@babynus)
Posts: 14952
Membre Admin
 

Planned days come from Planning Calculation, that you can run on Planning Gantt view.
Planning takes into account all constraints about Resource capacity, affectation rate, work assigned, assignment rate, planning mode for tasks, depedencies between tasks and priorities.


 
Posté : 17 Fév AM 01:022
 eric
(@chaussin)
Posts: 29
Active Member
Début du sujet
 

Thank you I guess I have undertood how it work


 
Posté : 17 Fév PM 21:022