resource already assigned on a recurring basis

6 Posts
2 Users
0 Reactions
1,340 Views
(@chaours)
Posts: 45
Active Member
Topic starter
 
[#7664]

Hello, why do I have this display when I validate a recurring assignment "resource already assigned on a recurring basis" thank you

***

bonjour,
pourquoi j'ai cet affichage lorsque je valide une assignation récurrente
"ressource déjà assignée de façon récurrente"
merci


 
Posted : 03 Aug 2021 18H17
Flou
 Flou
(@flou)
Posts: 253
Active Member
 

Hello,

you assigned the same source twice to the same activity on recurring mode ?


 
Posted : 03 Aug 2021 19H18
(@chaours)
Posts: 45
Active Member
Topic starter
 

mayby..


 
Posted : 03 Aug 2021 19H57
(@chaours)
Posts: 45
Active Member
Topic starter
 

ok but then how to handle the following:

I have a set of projects and in parallel with these projects I have recurring tasks for example management of emails and another task management of calls

***
ok mais alors comment gérer la chose suivante :

j'ai un ensemble de projet et en parrallèle de ces projets j'ai des taches réccurentes par exemple gestion des mails et une autre tache gestion des appels


 
Posted : 03 Aug 2021 20H02
Flou
 Flou
(@flou)
Posts: 253
Active Member
 

You crate two recurring activities on the same project and you assign your resource but you can't assign more than  capacity of your resource.


 
Posted : 03 Aug 2021 20H08
(@chaours)
Posts: 45
Active Member
Topic starter
 

in fact I am trying to do the following thing (I think I am not far from it in view of my last manipulations of the software):

I have 2 businesses,
on the one hand I have projects which work in phases and which are rather chronological, the phases of these various projects are followed from one project to another)
on the other hand I have a background activity relating to my other company
and finally basic activities of common management, emails, telephone, accounting ...

I am entering all this in order to be able to estimate at best the duration of the various activities

thank you

***
en fait je cherche à faire la chose suivante (je pense ne pas en être loin à la vue de mes derniere manipulations du logiciel ) :

j'ai 2 entrerpises,
d'une part j'ai des projet qui marchent par phases et qui sont plutot chronologiques, les phases de ces divers projets se suiven d'un projet à l'autres)
d'autre part j'ai une activité de fond relative à mon autre entreprise
et enfin des activités de base de gestion commune, mails, telephone, comptabilité ...

je suis en train de rentrer tout ça pour pouvoir estimer au mieux la durée des diverses activités

merci


 
Posted : 03 Aug 2021 20H09