Schedule activities

7 Posts
2 Users
0 Reactions
2,357 Views
(@fad)
Posts: 46
Active Member
Topic starter
 
[#8929]

Hi,

I don't understand why, is it impossible to assign time to my resource.
The resource is free this day (14/06/23), but the system message indicate that it'is impossible to plan the job because  the left time is not enough.

I'm surprise, something seems is wrong, but why ?

I have try to put the rate to 0%, but it still wrong...

Many thanks for your help,

Fred

 


 
Posted : 09 Jun 2023 15H35
(@alain-fourastie)
Posts: 366
Active Member Moderator
 

HI,
Have you also checked if a period has been allocated of this resource on this project ?
Have you thought to replan the planning ?


 
Posted : 09 Jun 2023 15H55
(@fad)
Posts: 46
Active Member
Topic starter
 

Hi,

Many thanks for your reply..

I didn't have end date of project. I have put end date date of project, but still the same behaviour..

I can't plan the job. It's the first task created on my project, and any task are planned.


 
Posted : 09 Jun 2023 16H31
(@alain-fourastie)
Posts: 366
Active Member Moderator
 

I asked you if your resource is allocated on projet with a limited period ?


 
Posted : 09 Jun 2023 17H20
(@fad)
Posts: 46
Active Member
Topic starter
 

Yes my resources is allocatedto the master project.

My project is sub project from another.

If the ressource will not available for the project, it' will be impossible to assign to the task.


 
Posted : 09 Jun 2023 17H37
(@alain-fourastie)
Posts: 366
Active Member Moderator
 

Be careful the rate is 0 on your pic below ; give a value and then ?
ok the limited period is good in our case


 
Posted : 09 Jun 2023 17H51
(@fad)
Posts: 46
Active Member
Topic starter
 

Hi,

Many thanks for your help, but anythink can solve it.

I have put a rate value but the task still in the same state.

I have already used the rate 0% when we have many task in parrallel without link between them !

Actually the task is post poned to 01/01/24.....and between today and 01/01/24 we have many free time for this resources,

Strange very strange this behaviour


 
Posted : 12 Jun 2023 9H35