Hi,
I don't understand why, is it impossible to assign time to my resource.
The resource is free this day (14/06/23), but the system message indicate that it'is impossible to plan the job because the left time is not enough.
I'm surprise, something seems is wrong, but why ?
I have try to put the rate to 0%, but it still wrong...
Many thanks for your help,
Fred
HI,
Have you also checked if a period has been allocated of this resource on this project ?
Have you thought to replan the planning ?
Hi,
Many thanks for your reply..
I didn't have end date of project. I have put end date date of project, but still the same behaviour..
I can't plan the job. It's the first task created on my project, and any task are planned.
I asked you if your resource is allocated on projet with a limited period ?
Be careful the rate is 0 on your pic below ; give a value and then ?
ok the limited period is good in our case
Hi,
Many thanks for your help, but anythink can solve it.
I have put a rate value but the task still in the same state.
I have already used the rate 0% when we have many task in parrallel without link between them !
Actually the task is post poned to 01/01/24.....and between today and 01/01/24 we have many free time for this resources,
Strange very strange this behaviour