Hi, I don't understand because in an activity planned date is red and not editable.
I set this activity with a start and end date validated. I assign activity to a resource setting only 100% rate (this resource has committed for now some real work days). In this activity duration is 19 days but in planned column duration is 30!!! Why? Where am I wrong?
Thamks
Found solution. I must manage correctly left work.