Forum

Report for function
 
Notifications
Retirer tout

Report for function

5 Posts
2 Utilisateurs
0 Reactions
3,719 Vu
(@igio80)
Posts: 30
Active Member
Début du sujet
 
[#2950]

Hello, is it possible get a report for resource function in a project?
I would like get a report for:

  1. time total for project (I believe that planning is best output)
  2. resource type (Developer, Manager, ecc.)
  3. resource total hour planned

Then, if a resource is for example to 10% on a parent task that contains a lot of activities, how can I get total hour planned for that resource?

Thanks.


 
Posté : 21 Jan PM 16:011
(@igio80)
Posts: 30
Active Member
Début du sujet
 

Is not possible?


 
Posté : 21 Jan PM 18:011
(@babynus)
Posts: 14952
Membre Admin
 

1) an 3) "Monthly planning resource/project" should do the job
2) I don't understand the need


 
Posté : 22 Jan PM 21:011
(@igio80)
Posts: 30
Active Member
Début du sujet
 

Thanks, so "Monthly planning resource/project" is ok but I must set for each activity an Assignment resource with a number of day assigned otherwise I don't see planned day. Is it right?
I have created some activities where I set only a validated duration (so Gantt update automatically for each activity change duration) with one or more assignment (with set only rate to 100%).
Point 2 (resource type (Developer, Manager, ecc.)) I mean that I add a "Functions" called "DBA" in "Lists of values". I would like assignment a resource for some activities with this function and I need of a report to estimate how time "DBA" is engaged on my project.
I hope I have been clear.
Thanks a lot.


 
Posté : 25 Jan AM 11:011
(@babynus)
Posts: 14952
Membre Admin
 

Thanks, so "Monthly planning resource/project" is ok but I must set for each activity an Assignment resource with a number of day assigned otherwise I don't see planned day. Is it right?

Yes.
ProjeQtOr is work driven.
You must define work (who works on which activity/task for how many days) to get a planning.

I have created some activities where I set only a validated duration (so Gantt update automatically for each activity change duration) with one or more assignment (with set only rate to 100%).

If you want a fixed duration, you need to set "planning mode" = "fixed duration", otherwise your validated duration is only informative when you set some assignments.

I mean that I add a "Functions" called "DBA" in "Lists of values". I would like assignment a resource for some activities with this function and I need of a report to estimate how time "DBA" is engaged on my project.

There is no report to get this. You'll have to build your own (or request for a quote if you want to have it built for you)


 
Posté : 25 Jan PM 12:011
Share:
Retour en haut