Forum

Welcome to ProjeQtOr new Forum. We migrated old forum to the new website.
You will find all your posts here, with your usual account.
Just one point : you’ll have to reinitialize your password. Use “Lost password” feature.

[SOLVED] Dispatch :...
 
Notifications
Clear all

[SOLVED] Dispatch : Real work can't bedefined over the 10000000000 days.

2 Posts
2 Users
0 Reactions
2,339 Views
(@bourle)
Posts: 26
Active Member
Topic starter
 
[#3683]

Hello.
I have an alert message when I do a "dispatch" in a ticket. (see screenshot : Real work can't bedefined over the 10000000000 days)
This is the only screen where I have a problem. In "real work allocation", I can change and save.
- I have the problem for all profiles
- My version of projeqtor is 5.5.1 (update 5.1.5 to 5.4.5 without error, and 5.4.5 to 5.5.1 with an error but similar at "error when upgrading 5.4.5 to 5.5..1" by dnaton)
- I have the same problem on new install in 5.5.1

I don't find the parameter I need to modify...

Thank you in advance for your return, and sorry for my english 🙂


 
Posted : 20 Sep 2016 21H05
ANOLL
(@krowry)
Posts: 131
Active Member
 

Hello ,

This bug was solved in version 5.5.2 !


 
Posted : 05 Oct 2016 11H11
Share:

Scroll to Top