[SOLVED] Link Project Product & Product Version: closed state

6 Posts
2 Users
0 Reactions
1,957 Views
Tony
 Tony
(@tony44)
Posts: 131
Active Member
Topic starter
 
[#7431]

Hi,

On a project, 'Configuration' section, we can link products and product versions.
On these links, it is possible to check a "closed" state, as below :

 

What are the expected behaviors / results when this box is checked :
- on the Project Product link ?
- on the Project Product version link ?

Is it expected that the product or version whose link to the project is closed is no longer available on the elements of the project ?
For example, the product version would no longer be offered in the 'original product version' and 'target product version' fields of a ticket for this project.
I see this is not the case, is this an issue ?

Thanks !


Tony44

 
Posted : 20 Mar 2021 3H25
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Hi,

Thiks is entended to work as you describe.
It it doesn't it is an issue.
We'll have a look.


 
Posted : 21 Mar 2021 15H56
Tony
 Tony
(@tony44)
Posts: 131
Active Member
Topic starter
 

Ok, Thanks.

Likewise, the "start date" and "end date" fields of these links are not taken into account : the product and the product version are available outside the validity period of the link defined by these dates.


Tony44

 
Posted : 22 Mar 2021 3H06
Tony
 Tony
(@tony44)
Posts: 131
Active Member
Topic starter
 

Hi,

In V9.1.2, the closed link is now well taken into account.

However, the “start date” and “end date” fields of these links are still not taken into account: the product and the product version are available outside the validity period of the link defined by these dates. 


Tony44

 
Posted : 08 Apr 2021 1H02
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

However, the “start date” and “end date” fields of these links are still not taken into account: the product and the product version are available outside the validity period of the link defined by these dates. 

These dates (displayed on project for linked versions) is not date for the link.
These are for information about dates of version. They have no impact on link availability.


 
Posted : 09 Apr 2021 17H30
Tony
 Tony
(@tony44)
Posts: 131
Active Member
Topic starter
 

Alright, that's fine with me.
In fact I had understood the opposite in the user manual :
 


Tony44

 
Posted : 10 Apr 2021 1H56
Share: