Hi,
On a project, 'Configuration' section, we can link products and product versions.
On these links, it is possible to check a "closed" state, as below :
What are the expected behaviors / results when this box is checked :
- on the Project Product link ?
- on the Project Product version link ?
Is it expected that the product or version whose link to the project is closed is no longer available on the elements of the project ?
For example, the product version would no longer be offered in the 'original product version' and 'target product version' fields of a ticket for this project.
I see this is not the case, is this an issue ?
Thanks !
Tony44
Hi,
Thiks is entended to work as you describe.
It it doesn't it is an issue.
We'll have a look.
Ok, Thanks.
Likewise, the "start date" and "end date" fields of these links are not taken into account : the product and the product version are available outside the validity period of the link defined by these dates.
Tony44
Hi,
In V9.1.2, the closed link is now well taken into account.
However, the “start date” and “end date” fields of these links are still not taken into account: the product and the product version are available outside the validity period of the link defined by these dates.
Tony44
However, the “start date” and “end date” fields of these links are still not taken into account: the product and the product version are available outside the validity period of the link defined by these dates.
These dates (displayed on project for linked versions) is not date for the link.
These are for information about dates of version. They have no impact on link availability.